Main Street Construction Schedule Update - June 2009
Week of June 8 – 12 The concrete sidewalks around Elm Square will continue to be poured. Musgrove Plaza will be the priority Monday through Wednesday. Other areas to have concrete poured include the...
View ArticleMain Street Construction Schedule Update - June 19, 2009
Week of June 22, 2009 Chestnut Street intersection will begin to have the new corner curbing and the pedestrian crossing lights installed. The drainage improvements for this area are slowly being...
View ArticleDowntown Crosswalks
The crosswalks in downtown will be under construction for the next few weeks (weather pending). It is one of the very last components to the project, however, people may say "why are they tearing up...
View ArticleDowntown Paving Schedule
Please be aware that the top coat paving will occur Tuesday, August 18, 2009 to Thursday, August 20, 2009 (pending any unforeseen circumstances). Tuesday: Locke Street to Chestnut Street Wednesday:...
View ArticleAndover Day 2009
Save the Date!! Saturday, October 3rd Andover Day 2009 Welcome Back to Main StreetAnd Know Your Town Fair Attractions include: Fashion shows on Main Street by your local boutiques Dance performances by...